City of Winnipeg's CentrePort South sewer project costs rise $13M

City of Winnipeg's CentrePort South sewer project costs rise $13M

The cost of extending water and sewer services to the future site of CentrePort South has risen by nearly $13 million in three years. A City of Winnipeg estimate in 2020 guessed the project would cost $61 million, with the Manitoba government announcing last year it would cover up to $40 million. Reasons for the increase include inflation in the construction industry, and the need to reroute a main feeder line due to an Indigenous burial mound, according to a report to the finance committee on Friday.